Summary
France’s Flamanville 3 nuclear reactor, its most powerful at 1,600 MW, was connected to the grid on December 21 after 17 years of construction plagued by delays and budget overruns.
The European Pressurized Reactor (EPR), designed to boost nuclear energy post-Chernobyl, is 12 years behind schedule and cost €13.2 billion, quadruple initial estimates.
President Macron hailed the launch as a key step for low-carbon energy and energy security.
Nuclear power, which supplies 60% of France’s electricity, is central to Macron’s plan for a “nuclear renaissance.”
At least this one is on the coast so it can still run when the rivers dry up.
But holy shitsnacks 3½ times slower than planned and 4 times more expensive. No wonder no new nuclear power plants have been built in a generation when the ones coming online now were all delayed by a generation.
4 times budget sounds more than it is. You have to underbid to actually get contracts for construction and then it also depends on what was actually missing in the specification.
Big projects are never on budget because the budget is just an arbitrary number of lowballing the best case estimate
Some anti nuclear groups do everything they can to slow down nuclear builds, putting as many road blocks in the way as possible. Then when it’s slow they say: see, building nuclear plants is slow!
Did the anti nuclear people inflate the cost fourfold, too?
Yes, impeding something is ultimately an increase in cost. That’s how it works.
The only miscalculation of the cost by -four times- was due to protest of anti nuclear protestors, according to you?
Source pls?
Source for what you said?..
For additional context, one of the reason for the delay and cost increase was the absurdly complex design due to French and German companies trying to collaborate on a new design as Germany was turning anti-nuclear, which culminated with Germany deciding to stop nuclear energy after the Fukushima Daiichi event.
Another big reason is the knowledge loss due to almost one generation without any reactor built in between.1.6 GW, cool, but everyone knows all you need is 1.21 GW
Olkiluoto unit 3 took 18 years: https://en.wikipedia.org/wiki/Olkiluoto_Nuclear_Power_Plant?wprov=sfti1
It’s the same French EPR tech and the whole project was plagued with mistakes because the French wanted to cut corners and just get it built as fast as possible.
Sounds like pretty much every software project I’ve ever worked on